Febbraio 2009
|
D.1.1. Kick-off workshop proceedings
|
| Febbraio 2009 |
D.7. Definition of the monitoring protocol, the monitoring indicators and source of verification |
| Marzo 2009 |
D.1.2. Detailed project work plan |
| Maggio 2009 |
D.8.1. Publication of web site for the project |
| Giugno 2009 |
D.9. Contingency Plan |
| Settembre 2009 |
D.2.1. Report on data collected and analyzed |
| Settembre 2009 |
Inception Report |
| Luglio 2010 |
D.4.1. Report on future climate scenarios defined for the case study area |
| Luglio 2010 |
D.4.2. Report on Sea level rise projections for the case study area |
| Gennaio 2010 |
Mid-term Report |
| Gennaio 2011 |
Progress Report n°1 |
| Gennaio 2011 |
D.2.2. Report on Esino River monitoring campaign |
| Gennaio 2011 |
D.2.1. Report on acquifer monitoring campaign |
| Febbraio 2011 |
D.2.2. Report on the GIS plus map of Iso-piezometric map of the current situation |
| Maggio 2011 |
D.3. Report on the costruction and calibration of integrated models |
| Settembre 2011 |
D.5. Report on remediation action simulated with the integrated models plus the expected thematic maps. |
| Settembre 2011 |
D.6.1. Report on scenarios construction for the Esino basin area |
| Settembre 2011 |
D.6.2. Report on definition of a Regional Risk Assessment methodology |
| Settembre 2011 |
D.6.3. Report on groundwater impact and risk assessment for the case study area sources of verification |
| Giugno 2011 |
D.8.3. Conferences material (invitations, papers, etc.) |
| Ottobre 2011 |
D.8.2. CD-ROMs containing project results |
| Dicembre 2011 |
D.8.3. Publication of project summary in specialised magazines |
| Gennaio 2012 |
D.10. Report of the independent auditor |
| Febbraio 2012 |
Final Report |
| |